Vantage Data Centers KUL2 Campus
Vantage Data Centers KUL2 Campus is an operational data center operated by Equinix in Cyberjaya, Malaysia. Our footprint estimate of its power is about 23 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Equinix |
| Facility power | 23 MW (range 9.3 MW to 58 MW) Estimate from building footprint, low confidence. Footprint estimate: about 193,097 m² site outline x 0.12 kW per m² of land. |
| GPU capacity if all AI | about 9,800 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Also known as | Equinix Data Center - Kuala Lumpur |
| Coordinates | 2.90401, 101.64973 |
Power and grid
| Nearest high-voltage substation | PMU GIS Cybersouth 4, 275 kV, 400 m away Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| HV substations within 10 km | 8 |
| Power plants within 50 km | 10 GW in 12 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 601 g CO₂ per kWh (Malaysia, 2025) Average of all power made in the area. Ember. |
| Grid power mix | coal 44.5%, gas 33.2%, hydro 16.3%, solar 3.9%, oil and other fossil 1.3%. Clean power: 21% |
Climate and water
| Average temperature | 27.8 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 33.2 °C (2001 to 2025) |
| Cooling degree days | 3,495 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.8 kWh per m² per day |
| Wind at 50 m | 3.1 m/s average |
| Water stress today | Low (<10%) (Selangor) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Vantage Data Centers KUL2 Campus use?
We estimate the facility power at about 23 MW. Estimate from building footprint, low confidence.
How close is Vantage Data Centers KUL2 Campus to the power grid?
The nearest high-voltage substation in OpenStreetMap is PMU GIS Cybersouth 4 (275 kV), about 400 m away.
How clean is the power for Vantage Data Centers KUL2 Campus?
The grid in Malaysia emits about 601 g CO₂ per kWh (2025). Largest sources: coal 44.5%, gas 33.2%, hydro 16.3%.
Who operates Vantage Data Centers KUL2 Campus?
Equinix.
Data centers near Cyberjaya
- CJ1 CYBERJAYA 252 m · 0.7 MW
- STTGDC KUL1 274 m · 0.7 MW
- Keppel Data Centres | Basis Bay Data Centre 371 m
- Damac Digital, Daria Data Centre KUL01 438 m · 6.6 MW
- Microsoft Datacenter KUL03 529 m · 19 MW
- Pi DC Datacenter 595 m · 3.5 MW
- Data Center KUL75 659 m · 14 MW
- Equinix KL02 Data Center 677 m · 9 MW
More Equinix data centers
- Equinix DA1 - Dallas United States
- Equinix SP6 Brazil
- Equinix PH1 - Philadelphia United States
- Equinix PA13X France
- Equinix CH1/CH2/CH4 - Chicago United States
- Equinix CH3 - Elk Grove United States
- Equinix AM3 - Amsterdam, Science Park Netherlands
- Equinix LA1 - Los Angeles United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.