CoreWeave Lancaster Greenfield site
CoreWeave Lancaster Greenfield site is a data center under construction operated by CoreWeave in PA, United States. No power figure is public for this site yet. Likely chips: NVIDIA GPUs (AMD possible) (guess).
Power demand is growing at this site
Key facts
| Status | Under construction |
|---|---|
| Operator | CoreWeave |
| Users | OpenAI (speculative) |
| Planned power | 124 MW by 2027-06-30 Epoch AI timeline projection. |
| AI chips | NVIDIA GPUs (AMD possible) Guess from the operator, not confirmed. GPU cloud and AI hosting firms mostly deploy NVIDIA, a few deploy AMD. |
| Investors | Blue Owl Capital |
| Address | 216 Greenfield Rd, Lancaster, PA |
| Coordinates | 40.04722, -76.25553 |
Power and grid
| Nearest high-voltage substation | North Bridgeport Substation, 138 kV, 100 m away (PPL) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | South Akron Substation, 230 kV, 11.3 km away |
| HV substations within 10 km | 15 |
| Utility | Ppl Electric Utilities Corp (investor owned) Electric retail service territory (HIFLD, US government). |
| Balancing authority | PJM |
| Nearest gas pipeline | Texas Eastern Trans Co, interstate pipeline, 1.4 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 12 GW in 32 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 387 g CO₂ per kWh (Pennsylvania, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 58%, nuclear 30.3%, coal 7.1%, wind 1.4%, solar 1.4%. Clean power: 34.3% |
| Industrial power price | USD 0.105 per kWh (Pennsylvania, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 11.5 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 39.2 °C (2001 to 2025) |
| Cooling degree days | 578 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.86 kWh per m² per day |
| Wind at 50 m | 4.9 m/s average |
| Water stress today | Low - Medium (10-20%) (Pennsylvania) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Build timeline
| Date | Power | H100e | What the satellite images and filings show |
|---|---|---|---|
| 2025-07-15 | 0 | 0 | [Coreweave announces $6 billion investment into Lancaster data centers, at two former printing press sites.](https://investors.coreweave.com/news/news-details/2025/CoreWeave-Announces-Multi-Billion-Dollar-Commitment-to-AI-Infrastructure-in-Pennsylvania/default.aspx) |
| 2026-07-13 | 0 | 0 | Cooling install continues on the roof, satellite imagery indicates that not all units have been completed. Continued presence of construction vehicles and unfinished land on the campus suggests that the building is not operational yet. |
| 2027-06-30 (projected) | 124 MW | 233,000 | [We estimate that Building 1 will be operational by Summer 2027 due to third party reporting.](https://www.witf.org/2025/08/28/lancaster-city-data-centers-face-zoning-hearing-possible-new-regulations/) |
Source: Epoch AI Frontier Data Centers.
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
What chips does CoreWeave Lancaster Greenfield site use?
No chips are reported. Based on the operator, the likely chips are NVIDIA GPUs (AMD possible).
How close is CoreWeave Lancaster Greenfield site to the power grid?
The nearest high-voltage substation in OpenStreetMap is North Bridgeport Substation (138 kV), about 100 m away. The local utility is Ppl Electric Utilities Corp, in the PJM balancing area.
How clean is the power for CoreWeave Lancaster Greenfield site?
The grid in Pennsylvania emits about 387 g CO₂ per kWh (2025). Largest sources: gas 58%, nuclear 30.3%, coal 7.1%.
Who operates CoreWeave Lancaster Greenfield site?
CoreWeave. Reported users: OpenAI.
Data centers near PA
- Omega PA1 39.0 km
- Direct LTx Reading 43.8 km
- USNAMES-NET 64.1 km
- IPR Wilmington CCC 69.0 km
- PDC1 - 9999 Hamilton blvd 75.1 km · 20 MW
More CoreWeave data centers
- Coreweave Helios United States
- CoreWeave Ellendale ND United States
- CoreWeave Denton TX United States
- CoreWeave Chester VA United States
- CoreWeave Muskogee OK United States
- CoreWeave Marble NC United States
- CoreWeave Norway Norway
- CoreWeave Dalton 1 & 2 United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.