CyrusOne data center in Fort Worth
CyrusOne data center in Fort Worth is an operational data center operated by CyrusOne in Fort Worth, United States. Our footprint estimate of its power is about 15 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | CyrusOne |
| Facility power | 15 MW (range 7.6 MW to 24 MW) Estimate from building footprint, low confidence. Footprint estimate: about 12,715 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 6,400 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Address | Ashphalt Road 9501, 76179, Fort Worth |
| Coordinates | 32.89912, -97.38895 |
Power and grid
| Nearest high-voltage substation | Unnamed substation, 138 kV, 500 m away Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Hicks Substation, 345 kV, 700 m away |
| HV substations within 10 km | 15 |
| Utility | Denton County Elec Coop, INC (cooperative) Electric retail service territory (HIFLD, US government). |
| Balancing authority | ERCO |
| Nearest gas pipeline | Energy Transfer, intrastate pipeline, 2.5 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 3.4 GW in 14 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 379 g CO₂ per kWh (Texas, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 48.3%, wind 21.7%, coal 11.6%, solar 10.7%, nuclear 7%. Clean power: 39.8% |
| Industrial power price | USD 0.072 per kWh (Texas, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 18.5 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 45.7 °C (2001 to 2025) |
| Cooling degree days | 1,585 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.81 kWh per m² per day |
| Wind at 50 m | 6.6 m/s average |
| Water stress today | High (40-80%) (Texas) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | High (40-80%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does CyrusOne data center in Fort Worth use?
We estimate the facility power at about 15 MW. Estimate from building footprint, low confidence.
How close is CyrusOne data center in Fort Worth to the power grid?
The nearest high-voltage substation in OpenStreetMap is an unnamed substation (138 kV), about 500 m away. The local utility is Denton County Elec Coop, INC, in the ERCO balancing area.
How clean is the power for CyrusOne data center in Fort Worth?
The grid in Texas emits about 379 g CO₂ per kWh (2025). Largest sources: gas 48.3%, wind 21.7%, coal 11.6%.
Who operates CyrusOne data center in Fort Worth?
CyrusOne.
Data centers near Fort Worth
- Facebook Fort Worth Datacenter 15.3 km · 163 MW
- TierPoint Dallas Forth Worth 15.6 km
- QTS Data Center 15.7 km · 37 MW
- Facebook Fort Worth Datacenter 15.7 km · 88 MW
- QTS Fort Worth (FTW1) 15.7 km
- Facebook Fort Worth Datacenter 15.9 km · 153 MW
- Alpheus Fort Worth (307 W 7th St) 17.3 km
- Charles Schwab Data Center 17.7 km · 7 MW
More CyrusOne data centers
- CyrusOne NVA5 United States
- CyrusOne FRA3 Germany
- CyrusOne Sterling United States
- CyrusOne Aurora I United States
- CyrusOne Sterling NVA9 United States
- CyrusOne NVA14 United States
- CyrusOne Lebanon United States
- CyrusOne NC-1 United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.