CyrusOne NC-1
CyrusOne NC-1 is an operational data center operated by CyrusOne in Durham, United States. Our footprint estimate of its power is about 43 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | CyrusOne |
| Facility power | 43 MW (range 21 MW to 68 MW) Estimate from building footprint, low confidence. Footprint estimate: about 35,462 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 18,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Networks | 6 networks PeeringDB. |
| Address | 2223 NE Creek Parkway |
| Coordinates | 35.93634, -78.87994 |
| Website | cyrusone.com/locations/north-carolina/north-carolina-data-center-raleigh-durham-i |
Power and grid
| Nearest high-voltage substation | Unnamed substation, 100 kV, 100 m away Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Unnamed substation, 230 kV, 5.8 km away |
| HV substations within 10 km | 33 |
| Utility | Duke Energy Carolinas, LLC (investor owned) Electric retail service territory (HIFLD, US government). |
| Balancing authority | DUK |
| Nearest gas pipeline | Public Service Co of NC, intrastate pipeline, 500 m away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 2.2 GW in 48 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 350 g CO₂ per kWh (North Carolina, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 39.7%, nuclear 31.5%, coal 13.1%, solar 10.1%, hydro 3.4%. Clean power: 46.9% |
| Industrial power price | USD 0.082 per kWh (North Carolina, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 15.4 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 41.7 °C (2001 to 2025) |
| Cooling degree days | 1,000 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.37 kWh per m² per day |
| Wind at 50 m | 4.3 m/s average |
| Water stress today | High (40-80%) (North Carolina) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | High (40-80%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does CyrusOne NC-1 use?
We estimate the facility power at about 43 MW. Estimate from building footprint, low confidence.
How close is CyrusOne NC-1 to the power grid?
The nearest high-voltage substation in OpenStreetMap is an unnamed substation (100 kV), about 100 m away. The local utility is Duke Energy Carolinas, LLC, in the DUK balancing area.
How clean is the power for CyrusOne NC-1?
The grid in North Carolina emits about 350 g CO₂ per kWh (2025). Largest sources: gas 39.7%, nuclear 31.5%, coal 13.1%.
Who operates CyrusOne NC-1?
CyrusOne.
Data centers near Durham
- CyrusOne data center in Durham 287 m · 8.3 MW
- TierPoint Research Triangle Park – RTP 4.4 km
- vXchnge Raleigh-Durham (NC01) 5.3 km
- Windstream Communications 6.6 km
- Brandaleone Lab for Data and Visualization 9.1 km
- Flexential - Raleigh (RAL01/02/03) 10.7 km
- iGLASS Networks 20.7 km · 1.1 MW
- American Tower RA1 21.5 km
More CyrusOne data centers
- CyrusOne NVA5 United States
- CyrusOne FRA3 Germany
- CyrusOne Sterling United States
- CyrusOne Aurora I United States
- CyrusOne Sterling NVA9 United States
- CyrusOne NVA14 United States
- CyrusOne Lebanon United States
- CyrusOne NJ-1 United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.