DXN Data Centre
DXN Data Centre is an operational data center in Concord West, Australia. Our footprint estimate of its power is about 7.4 MW.
Key facts
| Status | Operational |
|---|---|
| Facility power | 7.4 MW (range 3.7 MW to 12 MW) Estimate from building footprint, low confidence. Footprint estimate: about 6,138 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 3,200 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Address | Parkview Drive 5 |
| Coordinates | -33.84521, 151.07365 |
Power and grid
| Nearest high-voltage substation | Unnamed substation, 132 kV, 500 m away (Ausgrid) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Unnamed substation, 330 kV, 6.4 km away |
| HV substations within 10 km | 26 |
| Power plants within 50 km | 229 MW in 5 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 518 g CO₂ per kWh (Australia, 2025) Average of all power made in the area. Ember. |
| Grid power mix | coal 42.9%, solar 20.4%, gas 15.5%, wind 13.8%, hydro 4.4%. Clean power: 39.8% |
Climate and water
| Average temperature | 18.7 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 39.9 °C (2001 to 2025) |
| Cooling degree days | 673 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.65 kWh per m² per day |
| Wind at 50 m | 5.2 m/s average |
| Water stress today | High (40-80%) (New South Wales) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | High (40-80%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does DXN Data Centre use?
We estimate the facility power at about 7.4 MW. Estimate from building footprint, low confidence.
How close is DXN Data Centre to the power grid?
The nearest high-voltage substation in OpenStreetMap is an unnamed substation (132 kV), about 500 m away.
How clean is the power for DXN Data Centre?
The grid in Australia emits about 518 g CO₂ per kWh (2025). Largest sources: coal 42.9%, solar 20.4%, gas 15.5%.
Data centers near Concord West
- Fujitsu Homebush/Sydney Olympic Park 538 m · 8.1 MW
- TPG Telecom data center in Newington 2.0 km · 6.4 MW
- Equinix SY6 - Sydney (formerly Metronode Sydney 2) 2.1 km · 2 MW
- Equinix SY9x 4.3 km · 11 MW
- AirTrunk Sydney North 7.8 km · 26 MW
- NEXTDC S2 8.2 km · 7.8 MW
- Fujitsu North Ryde 8.4 km · 14 MW
- NEXTDC S1 8.5 km · 34 MW
Sources
Correct this page or get the data