Equinix NY1 - New York, Newark is an operational data center operated by Equinix in Newark, United States. Our footprint estimate of its power is about 12 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Equinix |
| Facility power | 12 MW (range 6.2 MW to 20 MW) Estimate from building footprint, low confidence. Footprint estimate: about 10,290 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 5,100 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Networks | 110 networks, 5 internet exchanges PeeringDB. |
| Also known as | 165 Halsey Meet-Me Room · FiberNet Telecom Group Newark - 165 Halsey · Level(3) Newark · DataBank Newark (EWR1) · Crown Castle Newark (165 Halsey) · 165 Halsey / Equinix NY1 / Databank EWR1 |
| Address | 165 Halsey St |
| Coordinates | 40.73684, -74.17340 |
| Website | equinix.com/locations/americas-colocation/united-states-colocation/new-york-data-centers/ny1 |
Power and grid
| Nearest high-voltage substation | Federal Sqaure Substation, 138 kV, 1.1 km away (PSE&G) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | McCarter Switching Station, 230 kV, 2 km away |
| HV substations within 10 km | 31 |
| Utility | Public Service Elec & Gas Co (investor owned) Electric retail service territory (HIFLD, US government). |
| Balancing authority | PJM |
| Nearest gas pipeline | Transcontinental Gas PL, interstate pipeline, 1.8 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 19 GW in 151 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 265 g CO₂ per kWh (New Jersey, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 45.8%, nuclear 43.2%, solar 9%, oil and other fossil 1.5%, bioenergy 0.9%. Clean power: 52.8% |
| Industrial power price | USD 0.162 per kWh (New Jersey, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 12.3 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 34.3 °C (2001 to 2025) |
| Cooling degree days | 481 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.01 kWh per m² per day |
| Wind at 50 m | 6.9 m/s average |
| Water stress today | Medium - High (20-40%) (New Jersey) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Medium - High (20-40%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Equinix NY1 - New York, Newark use?
We estimate the facility power at about 12 MW. Estimate from building footprint, low confidence.
How close is Equinix NY1 - New York, Newark to the power grid?
The nearest high-voltage substation in OpenStreetMap is Federal Sqaure Substation (138 kV), about 1.1 km away. The local utility is Public Service Elec & Gas Co, in the PJM balancing area.
How clean is the power for Equinix NY1 - New York, Newark?
The grid in New Jersey emits about 265 g CO₂ per kWh (2025). Largest sources: gas 45.8%, nuclear 43.2%, solar 9%.
Who operates Equinix NY1 - New York, Newark?
Equinix.
Data centers near Newark
- NJDC2 - 300 J F Kennedy Blvd 9.4 km · 64 MW
- Equinix NY2/NY4/NY5/NY6 - New York, Secaucus 9.7 km · 29 MW
- H5 Data Centers Secaucus (NJ01) 9.8 km
- Equinix NY3 - New York, Secaucus 9.8 km · 9.2 MW
- H5 Secaucus 9.9 km
- BT Radianz: 492 River Road 10.0 km · 17 MW
- InterServer Teb2 10.0 km
- Centersquare New Jersey (EWR5) 10.4 km · 21 MW
More Equinix data centers
- Equinix DA1 - Dallas United States
- Equinix SP6 Brazil
- Equinix PH1 - Philadelphia United States
- Equinix PA13X France
- Equinix CH1/CH2/CH4 - Chicago United States
- Equinix CH3 - Elk Grove United States
- Equinix AM3 - Amsterdam, Science Park Netherlands
- Equinix LA1 - Los Angeles United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.