H5 Data Centers Nashville
H5 Data Centers Nashville is an operational data center operated by H5 Data Centers in Nashville, United States. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | H5 Data Centers |
| Networks | 24 networks, 2 internet exchanges PeeringDB. |
| Address | 147 Fourth Avenue |
| Coordinates | 36.16263, -86.77867 |
| Website | h5datacenters.com/nashville-colocation.html |
Power and grid
| Nearest high-voltage substation | Unnamed substation, 161 kV, 3 km away (Tennessee Valley Authority) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Unnamed substation, 500 kV, 20.2 km away |
| HV substations within 10 km | 6 |
| Utility | Nashville Electric Service (municipal) Electric retail service territory (HIFLD, US government). |
| Balancing authority | TVA |
| Nearest gas pipeline | Gulf Xpress, interstate pipeline, 15.5 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 2.1 GW in 10 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 363 g CO₂ per kWh (Tennessee, 2025) Average of all power made in the area. Ember. |
| Grid power mix | nuclear 39.2%, coal 24.1%, gas 23.5%, hydro 10.5%, solar 1.9%. Clean power: 52.2% |
| Industrial power price | USD 0.069 per kWh (Tennessee, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 14.9 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 42.7 °C (2001 to 2025) |
| Cooling degree days | 923 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.23 kWh per m² per day |
| Wind at 50 m | 5.2 m/s average |
| Water stress today | Low - Medium (10-20%) (Tennessee) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is H5 Data Centers Nashville to the power grid?
The nearest high-voltage substation in OpenStreetMap is an unnamed substation (161 kV), about 3 km away. The local utility is Nashville Electric Service, in the TVA balancing area.
How clean is the power for H5 Data Centers Nashville?
The grid in Tennessee emits about 363 g CO₂ per kWh (2025). Largest sources: nuclear 39.2%, coal 24.1%, gas 23.5%.
Who operates H5 Data Centers Nashville?
H5 Data Centers.
Data centers near Nashville
- IRIS - Nashville 212 m
- XO Nashville 695 m
- Zayo Nashville - 209 10th Ave. S 900 m
- Data center in Nashville 2.8 km · 1.2 MW
- Level(3) Nashville (9th Ave) 3.7 km
- Tennessee Processing Center LLC 5.9 km · 8.6 MW
- Level(3) Nashville (Sidco Drive) 7.0 km
- EdgeConneX Nashville (EDCNAS01) 7.2 km
More H5 Data Centers data centers
- H5 Data Centers Ashburn United States
- H5 Data Centers Omaha United States
- H5 Data Centers Quincy United States
- H5 Data Centers Virginia (4030) United States
- H5 Data Centers Quincy 2/3 United States
- H5 Data Centers Minneapolis United States
- H5 Data Centers Phoenix United States
- H5 Data Centers San Antonio United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.