Iron Mountain LON-2
Iron Mountain LON-2 is an operational data center operated by Iron Mountain in Slough, United Kingdom. Our footprint estimate of its power is about 12 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Iron Mountain |
| Facility power | 12 MW (range 5.9 MW to 19 MW) Estimate from building footprint, low confidence. Footprint estimate: about 9,869 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 5,100 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Also known as | Iron Mountain LON-3 |
| Address | Buckingham Avenue 110, Slough |
| Coordinates | 51.52052, -0.62156 |
Power and grid
| Nearest high-voltage substation | Unnamed substation, 132 kV, 400 m away Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Iver Substation, 400 kV, 8.9 km away |
| HV substations within 10 km | 12 |
| Power plants within 50 km | 3.8 GW in 96 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 218 g CO₂ per kWh (United Kingdom, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 31.3%, wind 29.4%, bioenergy 13.9%, nuclear 12.4%, solar 6.6%. Clean power: 64.2% |
Climate and water
| Average temperature | 10.3 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 34.9 °C (2001 to 2025) |
| Cooling degree days | 53 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 2.94 kWh per m² per day |
| Wind at 50 m | 7.1 m/s average |
| Water stress today | Low - Medium (10-20%) (England) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Iron Mountain LON-2 use?
We estimate the facility power at about 12 MW. Estimate from building footprint, low confidence.
How close is Iron Mountain LON-2 to the power grid?
The nearest high-voltage substation in OpenStreetMap is an unnamed substation (132 kV), about 400 m away.
How clean is the power for Iron Mountain LON-2?
The grid in United Kingdom emits about 218 g CO₂ per kWh (2025). Largest sources: gas 31.3%, wind 29.4%, bioenergy 13.9%.
Who operates Iron Mountain LON-2?
Iron Mountain.
Data centers near Slough
- Equinix LD10 - London, Slough 227 m · 2.9 MW
- Rackspace Slough 228 m · 5.8 MW
- VIRTUS LONDON9 255 m · 34 MW
- VIRTUS London 4 257 m · 19 MW
- VIRTUS LONDON4 (Slough) 298 m
- CyrusOne London 1 326 m · 8.6 MW
- Digital Realty London LHR27 327 m
- VIRTUS London 11 368 m · 7.2 MW
More Iron Mountain data centers
- Iron Mountain Data Center - New Jersey (NJE-1) United States
- Iron Mountain data center in Sandston United States
- Iron Mountain Data Center - Manassas (VA-1) United States
- Iron Mountain FRA-1 Germany
- Iron Mountain VA-3 United States
- Iron Mountain Data Center - Manassas (VA-2) United States
- Iron Mountain VA-7 United States
- Iron Mountain Data Center - London (LON-1) United Kingdom
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.