QTS Atlanta-Metro (ATL1)
QTS Atlanta-Metro (ATL1) is an operational data center operated by QTS Realty Trust in Atlanta, United States. Our footprint estimate of its power is about 70 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | QTS Realty Trust |
| Facility power | 70 MW (range 35 MW to 112 MW) Estimate from building footprint, low confidence. Footprint estimate: about 58,197 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 30,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Networks | 22 networks, 2 internet exchanges PeeringDB. |
| Also known as | QTS Atlanta Data Center 1 |
| Address | 1033 Jefferson St. NW |
| Coordinates | 33.77753, -84.42104 |
| Website | qtsdatacenters.com/data-centers/atlanta-metro |
Power and grid
| Nearest high-voltage substation | QTS Substation #2, 115 kV, 300 m away (Georgia Power) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Unnamed substation, 230 kV, 900 m away |
| HV substations within 10 km | 52 |
| Utility | Georgia Power Co (investor owned) Electric retail service territory (HIFLD, US government). |
| Balancing authority | SOCO |
| Nearest gas pipeline | Southern Natural Gas Co, interstate pipeline, 7.1 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 2.9 GW in 8 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 352 g CO₂ per kWh (Georgia, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 38.7%, nuclear 34.8%, coal 13.6%, solar 8.1%, bioenergy 3.2%. Clean power: 47.6% |
| Industrial power price | USD 0.131 per kWh (Georgia, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 16.1 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 42.1 °C (2001 to 2025) |
| Cooling degree days | 1,020 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.43 kWh per m² per day |
| Wind at 50 m | 4.5 m/s average |
| Water stress today | Medium - High (20-40%) (Georgia) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Medium - High (20-40%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does QTS Atlanta-Metro (ATL1) use?
We estimate the facility power at about 70 MW. Estimate from building footprint, low confidence.
How close is QTS Atlanta-Metro (ATL1) to the power grid?
The nearest high-voltage substation in OpenStreetMap is QTS Substation #2 (115 kV), about 300 m away. The local utility is Georgia Power Co, in the SOCO balancing area.
How clean is the power for QTS Atlanta-Metro (ATL1)?
The grid in Georgia emits about 352 g CO₂ per kWh (2025). Largest sources: gas 38.7%, nuclear 34.8%, coal 13.6%.
Who operates QTS Atlanta-Metro (ATL1)?
QTS Realty Trust.
Data centers near Atlanta
- xAI QTS Atlanta 142 m · 24 MW
- Data center in Atlanta 524 m · 17 MW
- Data center in Atlanta 565 m · 25 MW
- Databank Atlanta (ATL1) 3.1 km
- Digital Realty ATL14 - Atlanta 3.3 km
- Southern Telecom 3.5 km
- Equinix AT2/AT3 - Atlanta 3.7 km
- Colo at 55, LLC 3.7 km
More QTS Realty Trust data centers
- QTS Atlanta-Suwanee (SUW1) United States
- QTS Irving - Dallas (DFW1) United States
- QTS Chicago (CHI1) United States
- QTS Atlanta-Fayetteville (ATL2) United States
- QTS Eemshaven (EEM1) Netherlands
- QTS Sacramento (SAC1) United States
- QTS Ashburn (ASH1) United States
- QTS Santa Clara (SJC1/SJC2) United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.