Verizon data center in Minneapolis
Verizon data center in Minneapolis is an operational data center operated by Verizon in Minneapolis, United States. Our footprint estimate of its power is about 6.8 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Verizon |
| Facility power | 6.8 MW (range 3.4 MW to 11 MW) Estimate from building footprint, low confidence. Footprint estimate: about 5,690 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 2,900 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Address | North Washington Avenue 1200, 55401, Minneapolis |
| Coordinates | 44.99144, -93.28034 |
Power and grid
| Nearest high-voltage substation | 5th Street Substation, 115 kV, 1.5 km away Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Terminal Substation, 345 kV, 5.8 km away |
| HV substations within 10 km | 11 |
| Utility | City Of St Paul Electric retail service territory (HIFLD, US government). |
| Balancing authority | SWPP |
| Nearest gas pipeline | Northern Natural Gas Co, interstate pipeline, 11.5 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 4.1 GW in 73 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 460 g CO₂ per kWh (Nebraska, 2025) Average of all power made in the area. Ember. |
| Grid power mix | coal 46%, wind 29.4%, nuclear 17.4%, gas 3.2%, hydro 2.9%. Clean power: 50.7% |
| Industrial power price | USD 0.084 per kWh (Nebraska, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 7 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 41.6 °C (2001 to 2025) |
| Cooling degree days | 347 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.8 kWh per m² per day |
| Wind at 50 m | 6.8 m/s average |
| Water stress today | Extremely High (>80%) (Nebraska) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Extremely High (>80%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Verizon data center in Minneapolis use?
We estimate the facility power at about 6.8 MW. Estimate from building footprint, low confidence.
How close is Verizon data center in Minneapolis to the power grid?
The nearest high-voltage substation in OpenStreetMap is 5th Street Substation (115 kV), about 1.5 km away. The local utility is City Of St Paul, in the SWPP balancing area.
How clean is the power for Verizon data center in Minneapolis?
The grid in Nebraska emits about 460 g CO₂ per kWh (2025). Largest sources: coal 46%, wind 29.4%, nuclear 17.4%.
Who operates Verizon data center in Minneapolis?
Verizon.
Data centers near Minneapolis
- Lumen Minneapolis 3 418 m · 2.3 MW
- Implex Minneapolis 1.5 km
- Atomic Data MSP250 1.5 km
- TriTech Center 1.8 km
- T5@Minneapolis 2.4 km
- Cologix MIN1 3.0 km · 15 MW
- University of Minnesota Agate 3.9 km · 0.2 MW
- Advanced Operations Center 4.4 km · 2.1 MW
More Verizon data centers
- Verizon Freehold Data Center United States
- Verizon data center in Amsterdam-Zuidoost Netherlands
- Verizon UK5 United Kingdom
- Verizon Branchburg NEC Datacenter United States
- Verizon - Bloomington Network United States
- Verizon UK4 United Kingdom
- Verizon Luxembourg Luxembourg
- Verizon data center in Narrabundah Australia
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.