801 Main Street - Lenoir
801 Main Street - Lenoir is an operational data center operated by Dacentec in Lenoir, United States. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | Dacentec |
| Networks | 1 networks PeeringDB. |
| Address | 801 Main Street NW |
| Coordinates | 35.92248, -81.54274 |
| Website | dacentec.com |
Power and grid
| Nearest high-voltage substation | Unnamed substation, 100 kV, 3.1 km away Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Longview Substation, 230 kV, 25.4 km away |
| HV substations within 10 km | 7 |
| Utility | Blue Ridge Elec Member Corp (cooperative) Electric retail service territory (HIFLD, US government). |
| Balancing authority | DUK |
| Power plants within 50 km | 328 MW in 29 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 350 g CO₂ per kWh (North Carolina, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 39.7%, nuclear 31.5%, coal 13.1%, solar 10.1%, hydro 3.4%. Clean power: 46.9% |
| Industrial power price | USD 0.082 per kWh (North Carolina, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 13.9 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 39.8 °C (2001 to 2025) |
| Cooling degree days | 747 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.23 kWh per m² per day |
| Wind at 50 m | 4.4 m/s average |
| Water stress today | High (40-80%) (North Carolina) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | High (40-80%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is 801 Main Street - Lenoir to the power grid?
The nearest high-voltage substation in OpenStreetMap is an unnamed substation (100 kV), about 3.1 km away. The local utility is Blue Ridge Elec Member Corp, in the DUK balancing area.
How clean is the power for 801 Main Street - Lenoir?
The grid in North Carolina emits about 350 g CO₂ per kWh (2025). Largest sources: gas 39.7%, nuclear 31.5%, coal 13.1%.
Who operates 801 Main Street - Lenoir?
Dacentec.
Data centers near Lenoir
- Google Lenoir Data Center 2.7 km · 17 MW
- Google Project Cardinal 3.3 km · 40 MW
- Data center in Newton 44.6 km · 58 MW
- Apple - Maiden Data Center 44.9 km · 87 MW
- Data center in Newton 45.2 km · 53 MW
- Meta Forest City Data Center 72.1 km · 64 MW
- Meta 72.2 km · 71 MW
- T5@Charlotte 75.9 km · 5.8 MW
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.