Data Center Directory

Flexential - Cincinnati (CIN1/2)

Flexential - Cincinnati (CIN1/2) is an operational data center operated by Flexential in West Chester, United States. No power figure is public for this site yet.

Key facts

StatusOperational
OperatorFlexential
Networks2 networks, 1 internet exchanges
PeeringDB.
Also known asFlexential Cincinnati
Address5307 Muhlhauser Road
Coordinates39.31645, -84.45017
Websiteflexential.com

Power and grid

Nearest high-voltage substationPort Union Substation, 345 kV, 1.2 km away (Duke Energy)
Straight-line distance. OpenStreetMap, substations of 100 kV and more.
HV substations within 10 km8
UtilityDuke Energy Ohio INC (investor owned)
Electric retail service territory (HIFLD, US government).
Balancing authorityPJM
Nearest gas pipelineTexas Gas Transmission Co, interstate pipeline, 8.1 km away
US Energy Information Administration pipeline map. Straight-line distance.
Power plants within 50 km4.6 GW in 17 plants
Plants with a stated output in OpenStreetMap. The largest four are listed.
Grid carbon intensity536 g CO₂ per kWh (Ohio, 2025)
Average of all power made in the area. Ember.
Grid power mixgas 54.9%, coal 24.4%, nuclear 11.7%, solar 5.8%, wind 2%. Clean power: 20%
Industrial power priceUSD 0.098 per kWh (Ohio, August 2026)
Average price paid by industrial users in the state. EIA Electric Power Monthly.

Climate and water

Average temperature11.6 °C
NASA POWER, average of 2001 to 2025.
Highest temperature38.9 °C (2001 to 2025)
Cooling degree days573 per year (base 18.3 °C)
More cooling degree days means more energy for cooling.
Solar energy3.99 kWh per m² per day
Wind at 50 m6.1 m/s average
Water stress todayLow - Medium (10-20%) (Ohio)
Share of the local water supply that people already use. WRI Aqueduct 4.0, province level.
Water stress in 2050Low - Medium (10-20%)
Business-as-usual scenario.

Satellite view

Questions

How close is Flexential - Cincinnati (CIN1/2) to the power grid?

The nearest high-voltage substation in OpenStreetMap is Port Union Substation (345 kV), about 1.2 km away. The local utility is Duke Energy Ohio INC, in the PJM balancing area.

How clean is the power for Flexential - Cincinnati (CIN1/2)?

The grid in Ohio emits about 536 g CO₂ per kWh (2025). Largest sources: gas 54.9%, coal 24.4%, nuclear 11.7%.

Who operates Flexential - Cincinnati (CIN1/2)?

Flexential.

Data centers near West Chester

More Flexential data centers

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.