Data Center Directory

Google Berkeley County Data Center

Google Berkeley County Data Center is an operational data center operated by Google in Goose Creek, United States. Our footprint estimate of its power is about 82 MW. Likely chips: Google TPU (plus NVIDIA GPUs for cloud customers) (guess).

Key facts

StatusOperational
OperatorGoogle
Facility power82 MW (range 33 MW to 204 MW)
Estimate from building footprint, low confidence. Footprint estimate: about 681,511 m² site outline x 0.12 kW per m² of land.
AI chipsGoogle TPU (plus NVIDIA GPUs for cloud customers)
Guess from the operator, not confirmed. Google runs most of its AI work on its own TPU chips.
GPU capacity if all AIabout 35,000 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Also known asGoogle
Coordinates33.06395, -80.04254

Power and grid

Nearest high-voltage substationGoogle Substation #1, 115 kV, 200 m away
Straight-line distance. OpenStreetMap, substations of 100 kV and more.
Nearest 220 kV+ substationMount Holly Smeltery Substation, 230 kV, 2 km away
HV substations within 10 km15
UtilityBerkeley Electric Coop INC (cooperative)
Electric retail service territory (HIFLD, US government).
Balancing authoritySC
Nearest gas pipelineSouth Carolina PL Corp, interstate pipeline, 10.1 km away
US Energy Information Administration pipeline map. Straight-line distance.
Power plants within 50 km3.5 GW in 8 plants
Plants with a stated output in OpenStreetMap. The largest four are listed.
Grid carbon intensity288 g CO₂ per kWh (South Carolina, 2025)
Average of all power made in the area. Ember.
Grid power mixnuclear 53.9%, gas 21.4%, coal 17.3%, solar 3.8%, hydro 2.1%. Clean power: 61.3%
Industrial power priceUSD 0.079 per kWh (South Carolina, August 2026)
Average price paid by industrial users in the state. EIA Electric Power Monthly.

Climate and water

Average temperature19 °C
NASA POWER, average of 2001 to 2025.
Highest temperature39.1 °C (2001 to 2025)
Cooling degree days1,411 per year (base 18.3 °C)
More cooling degree days means more energy for cooling.
Solar energy4.62 kWh per m² per day
Wind at 50 m4.8 m/s average
Water stress todayMedium - High (20-40%) (South Carolina)
Share of the local water supply that people already use. WRI Aqueduct 4.0, province level.
Water stress in 2050Medium - High (20-40%)
Business-as-usual scenario.

Satellite view

Questions

How much power does Google Berkeley County Data Center use?

We estimate the facility power at about 82 MW. Estimate from building footprint, low confidence.

What chips does Google Berkeley County Data Center use?

No chips are reported. Based on the operator, the likely chips are Google TPU (plus NVIDIA GPUs for cloud customers).

How close is Google Berkeley County Data Center to the power grid?

The nearest high-voltage substation in OpenStreetMap is Google Substation #1 (115 kV), about 200 m away. The local utility is Berkeley Electric Coop INC, in the SC balancing area.

How clean is the power for Google Berkeley County Data Center?

The grid in South Carolina emits about 288 g CO₂ per kWh (2025). Largest sources: nuclear 53.9%, gas 21.4%, coal 17.3%.

Who operates Google Berkeley County Data Center?

Google.

Data centers near Goose Creek

More Google data centers

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.