Level(3) Oakland
Level(3) Oakland is an operational data center operated by Lumen Technologies in Emeryville, United States. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | Lumen Technologies |
| Networks | 2 networks PeeringDB. |
| Address | 5000 Hollis Ave |
| Coordinates | 37.83467, -122.28660 |
| Website | level3.net |
Power and grid
| Nearest high-voltage substation | Oakland D Substation, 115 kV, 2 km away (Pacific Gas and Electric Company) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Sobrante Substation, 230 kV, 10.5 km away |
| HV substations within 10 km | 14 |
| Utility | Pacific Gas & Electric Co. (investor owned) Electric retail service territory (HIFLD, US government). |
| Balancing authority | CISO |
| Nearest gas pipeline | California Gas Transmission Co, intrastate pipeline, 4.5 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 3.4 GW in 34 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 189 g CO₂ per kWh (California, 2025) Average of all power made in the area. Ember. |
| Grid power mix | solar 37.4%, gas 30.4%, hydro 11.7%, nuclear 7.3%, wind 6.7%. Clean power: 69.7% |
| Industrial power price | USD 0.241 per kWh (California, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 13.6 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 39 °C (2001 to 2025) |
| Cooling degree days | 95 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 5.14 kWh per m² per day |
| Wind at 50 m | 4.9 m/s average |
| Water stress today | Extremely High (>80%) (California) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Extremely High (>80%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is Level(3) Oakland to the power grid?
The nearest high-voltage substation in OpenStreetMap is Oakland D Substation (115 kV), about 2 km away. The local utility is Pacific Gas & Electric Co., in the CISO balancing area.
How clean is the power for Level(3) Oakland?
The grid in California emits about 189 g CO₂ per kWh (2025). Largest sources: solar 37.4%, gas 30.4%, hydro 11.7%.
Who operates Level(3) Oakland?
Lumen Technologies.
Data centers near Emeryville
- Evocative Emeryville (EM1) 1.5 km
- Digital Realty OAK (720 2nd St) 4.0 km · 20 MW
- Open Computing Facility 4.6 km
- Lawrence Berkeley NL NERSC Perlmutter 5.8 km · 6.9 MW
- Digital Realty SFO (365 Main) 10.5 km · 7.3 MW
- FedConnect San Francisco 10.9 km
- 274 Brannan Street 10.9 km
- TelePacific 11.3 km
More Lumen Technologies data centers
- Level(3) Weehawken United States
- Level(3) Seattle (Denny Way) United States
- Level(3) Denver United States
- Level(3) London (Braham Street) United Kingdom
- Level(3) McLean United States
- Lumen Ashburn United States
- Level(3) Sunnyvale United States
- Level(3) Dallas United States
Sources
Correct this page or get the data