Data Center Directory

Microsoft Bison Business Park Data Center

Microsoft Bison Business Park Data Center is an operational data center operated by Microsoft in Cheyenne, United States. Our footprint estimate of its power is about 94 MW. Likely chips: NVIDIA GPUs (some Microsoft Maia) (guess).

Key facts

StatusOperational
OperatorMicrosoft
Facility power94 MW (range 37 MW to 234 MW)
Estimate from building footprint, low confidence. Footprint estimate: about 780,740 m² site outline x 0.12 kW per m² of land.
AI chipsNVIDIA GPUs (some Microsoft Maia)
Guess from the operator, not confirmed. Microsoft AI capacity is mostly NVIDIA, with a few in-house Maia chips.
GPU capacity if all AIabout 40,000 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Coordinates41.06236, -104.78527

Power and grid

Nearest high-voltage substationBison Substation, 115 kV, 500 m away (Cheyenne Light Fuel and Power)
Straight-line distance. OpenStreetMap, substations of 100 kV and more.
Nearest 220 kV+ substationTerry Ranch Road Substation, 230 kV, 2.8 km away
HV substations within 10 km10
UtilityCheyenne Light Fuel & Power (investor owned)
Electric retail service territory (HIFLD, US government).
Balancing authorityWACM
Nearest gas pipelineSouthern Star Central Gas PL Co, interstate pipeline, 11.9 km away
US Energy Information Administration pipeline map. Straight-line distance.
Power plants within 50 km1.3 GW in 6 plants
Plants with a stated output in OpenStreetMap. The largest four are listed.
Grid carbon intensity620 g CO₂ per kWh (Wyoming, 2025)
Average of all power made in the area. Ember.
Grid power mixcoal 58.5%, wind 27.1%, gas 10%, hydro 2.1%, solar 1.2%. Clean power: 30.4%
Industrial power priceUSD 0.088 per kWh (Wyoming, August 2026)
Average price paid by industrial users in the state. EIA Electric Power Monthly.

Climate and water

Average temperature8.2 °C
NASA POWER, average of 2001 to 2025.
Highest temperature37.4 °C (2001 to 2025)
Cooling degree days304 per year (base 18.3 °C)
More cooling degree days means more energy for cooling.
Solar energy4.57 kWh per m² per day
Wind at 50 m7.1 m/s average
Water stress todayHigh (40-80%) (Wyoming)
Share of the local water supply that people already use. WRI Aqueduct 4.0, province level.
Water stress in 2050High (40-80%)
Business-as-usual scenario.

Satellite view

Questions

How much power does Microsoft Bison Business Park Data Center use?

We estimate the facility power at about 94 MW. Estimate from building footprint, low confidence.

What chips does Microsoft Bison Business Park Data Center use?

No chips are reported. Based on the operator, the likely chips are NVIDIA GPUs (some Microsoft Maia).

How close is Microsoft Bison Business Park Data Center to the power grid?

The nearest high-voltage substation in OpenStreetMap is Bison Substation (115 kV), about 500 m away. The local utility is Cheyenne Light Fuel & Power, in the WACM balancing area.

How clean is the power for Microsoft Bison Business Park Data Center?

The grid in Wyoming emits about 620 g CO₂ per kWh (2025). Largest sources: coal 58.5%, wind 27.1%, gas 10%.

Who operates Microsoft Bison Business Park Data Center?

Microsoft.

Data centers near Cheyenne

More Microsoft data centers

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.