Microsoft TRP3 (SAT46)
Microsoft TRP3 (SAT46) is an operational data center operated by Microsoft in Lackland Air Force Base, United States. Our footprint estimate of its power is about 19 MW. Likely chips: NVIDIA GPUs (some Microsoft Maia) (guess).
Key facts
| Status | Operational |
|---|---|
| Operator | Microsoft |
| Facility power | 19 MW (range 9.7 MW to 31 MW) Estimate from building footprint, low confidence. Footprint estimate: about 16,130 m² building outline x 1 floor(s) x 1.2 kW/m². |
| AI chips | NVIDIA GPUs (some Microsoft Maia) Guess from the operator, not confirmed. Microsoft AI capacity is mostly NVIDIA, with a few in-house Maia chips. |
| GPU capacity if all AI | about 8,100 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Coordinates | 29.41298, -98.80637 |
Power and grid
| Nearest high-voltage substation | Rafter Substation, 138 kV, 400 m away (CPS Energy) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Cagnon Road Substation, 345 kV, 8.5 km away |
| HV substations within 10 km | 5 |
| Utility | Bandera Electric Coop, INC (cooperative) Electric retail service territory (HIFLD, US government). |
| Balancing authority | ERCO |
| Nearest gas pipeline | El Paso Texas Pipeline Co, intrastate pipeline, 7.8 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 5.0 GW in 22 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 379 g CO₂ per kWh (Texas, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 48.3%, wind 21.7%, coal 11.6%, solar 10.7%, nuclear 7%. Clean power: 39.8% |
| Industrial power price | USD 0.072 per kWh (Texas, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 20.6 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 44.5 °C (2001 to 2025) |
| Cooling degree days | 1,804 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.84 kWh per m² per day |
| Wind at 50 m | 6.1 m/s average |
| Water stress today | High (40-80%) (Texas) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | High (40-80%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Microsoft TRP3 (SAT46) use?
We estimate the facility power at about 19 MW. Estimate from building footprint, low confidence.
What chips does Microsoft TRP3 (SAT46) use?
No chips are reported. Based on the operator, the likely chips are NVIDIA GPUs (some Microsoft Maia).
How close is Microsoft TRP3 (SAT46) to the power grid?
The nearest high-voltage substation in OpenStreetMap is Rafter Substation (138 kV), about 400 m away. The local utility is Bandera Electric Coop, INC, in the ERCO balancing area.
How clean is the power for Microsoft TRP3 (SAT46)?
The grid in Texas emits about 379 g CO₂ per kWh (2025). Largest sources: gas 48.3%, wind 21.7%, coal 11.6%.
Who operates Microsoft TRP3 (SAT46)?
Microsoft.
Data centers near Lackland Air Force Base
- Microsoft TRP1 369 m · 15 MW
- Microsoft Texas Research Park Campus 384 m · 87 MW
- Microsoft 745 m · 31 MW
- Vantage TX1 1.6 km · 45 MW
- CyrusOne SAT10 & SAT11 1.9 km · 12 MW
- Data center in Lackland Air Force Base 2.0 km · 21 MW
- Microsoft SAT 81 7.0 km · 21 MW
- Data center in Leon Valley 9.8 km · 14 MW
More Microsoft data centers
- Microsoft Fairwater Wisconsin United States
- Crusoe Abilene Expansion United States
- Microsoft Fairwater Atlanta United States
- Microsoft Goodyear United States
- Microsoft Boydton Data Center United States
- Microsoft Project Osmium United States
- OpenAI/Microsoft Goodyear Arizona United States
- Microsoft CYS Datacenter United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.