nLighten Gent BRU1
nLighten Gent BRU1 is an operational data center operated by nLighten HQ in Merelbeke, Belgium. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | nLighten HQ |
| Networks | 8 networks, 1 internet exchanges PeeringDB. |
| Address | Industriepark 2H |
| Coordinates | 50.98766, 3.76760 |
| Website | nlighten.com/en/belgium-data-centers/ghent |
Power and grid
| Nearest high-voltage substation | Flora, 150 kV, 3.9 km away (Elia) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Rodenhuize, 380 kV, 16 km away |
| HV substations within 10 km | 4 |
| Power plants within 50 km | 4.2 GW in 36 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 151 g CO₂ per kWh (Belgium, 2025) Average of all power made in the area. Ember. |
| Grid power mix | nuclear 33.5%, gas 20.8%, wind 18.6%, solar 14.5%, oil and other fossil 7.1%. Clean power: 72.1% |
| Industrial power price | EUR 0.133 per kWh (Belgium, 2026-S1) Non-household users with 20 to 70 GWh per year, without VAT. Eurostat. |
Climate and water
| Average temperature | 10.4 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 36.4 °C (2001 to 2025) |
| Cooling degree days | 66 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.03 kWh per m² per day |
| Wind at 50 m | 6.8 m/s average |
| Water stress today | Extremely High (>80%) (Belgium) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | Extremely High (>80%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is nLighten Gent BRU1 to the power grid?
The nearest high-voltage substation in OpenStreetMap is Flora (150 kV), about 3.9 km away.
How clean is the power for nLighten Gent BRU1?
The grid in Belgium emits about 151 g CO₂ per kWh (2025). Largest sources: nuclear 33.5%, gas 20.8%, wind 18.6%.
Who operates nLighten Gent BRU1?
nLighten HQ.
Data centers near Merelbeke
- Ghent Edge Data Center 77 m
- S10 5.6 km · 7.1 MW
- DCstar Datacenter Gent DCG 7.3 km · 3 MW
- Versatel Gent (Handelsdok Center) 8.8 km
- LCL Brussels West 20.7 km · 7 MW
- Penta Infra Brussel BRU01 38.4 km · 2 MW
- Datacenter Oostkamp 42.1 km · 3.3 MW
- DCstar Datacenter Oostkamp DCO 42.2 km
More nLighten HQ data centers
- nLighten Swindon BRS2 United Kingdom
- nLighten Leeds LBA1 United Kingdom
- nLighten Strasbourg SXB1 France
- nLighten Besancon MLH1 France
- nLighten Liverpool LPL1 United Kingdom
- nLighten Paris PAR2 France
- nLighten Sophia Antipolis NCE1 France
- nLighten Paris PAR1 France
Sources
Correct this page or get the data