Telstra
Telstra is an operational data center operated by Telstra in Erskine Park, Australia. Our footprint estimate of its power is about 24 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Telstra |
| Facility power | 24 MW (range 12 MW to 39 MW) Estimate from building footprint, low confidence. Footprint estimate: about 20,118 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 10,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Coordinates | -33.83089, 150.79488 |
Power and grid
| Nearest high-voltage substation | South Erskine Park Zone Substation, 132 kV, 700 m away (Endeavour Energy) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Sydney West Bulk Supply Substation, 330 kV, 3.5 km away |
| HV substations within 10 km | 16 |
| Power plants within 50 km | 229 MW in 5 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 518 g CO₂ per kWh (Australia, 2025) Average of all power made in the area. Ember. |
| Grid power mix | coal 42.9%, solar 20.4%, gas 15.5%, wind 13.8%, hydro 4.4%. Clean power: 39.8% |
Climate and water
| Average temperature | 18.7 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 39.9 °C (2001 to 2025) |
| Cooling degree days | 673 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 4.65 kWh per m² per day |
| Wind at 50 m | 5.2 m/s average |
| Water stress today | High (40-80%) (New South Wales) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | High (40-80%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Telstra use?
We estimate the facility power at about 24 MW. Estimate from building footprint, low confidence.
How close is Telstra to the power grid?
The nearest high-voltage substation in OpenStreetMap is South Erskine Park Zone Substation (132 kV), about 700 m away.
How clean is the power for Telstra?
The grid in Australia emits about 518 g CO₂ per kWh (2025). Largest sources: coal 42.9%, solar 20.4%, gas 15.5%.
Who operates Telstra?
Telstra.
Data centers near Erskine Park
- Digital Realty Sydney SYD10 1.6 km · 12 MW
- Microsoft SYD06 Data Centre 1.9 km · 20 MW
- CDC Eastern Creek Campus EC5 4.1 km · 14 MW
- CDC Eastern Creek Campus EC4 4.2 km · 17 MW
- CDC Sydney EC1 4.3 km · 17 MW
- Data center in Minchinbury 4.6 km · 12 MW
- AWS Asia Pacific (Sydney) Region Data Centre 4.7 km · 10 MW
- AWS Asia Pacific (Sydney) Region Data Centre 8.0 km · 14 MW
More Telstra data centers
- Telstra InfraCo - St Leonards Data Centre Australia
- Telstra Clayton Data Centre Australia
- Telstra Australia
- Telstra InfraCo - Clayton Data Centre Australia
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.