AWS Swindon Data Centre
AWS Swindon Data Centre is an operational data center operated by Amazon Web Services in Swindon, United Kingdom. Our footprint estimate of its power is about 14 MW. Likely chips: AWS Trainium and NVIDIA GPUs (guess).
Key facts
| Status | Operational |
|---|---|
| Operator | Amazon Web Services |
| Facility power | 14 MW (range 7 MW to 22 MW) Estimate from building footprint, low confidence. Footprint estimate: about 11,628 m² building outline x 1 floor(s) x 1.2 kW/m². |
| AI chips | AWS Trainium and NVIDIA GPUs Guess from the operator, not confirmed. AWS deploys its own Trainium chips next to NVIDIA GPUs. |
| GPU capacity if all AI | about 6,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Address | Burderop, SN4 0QB, Swindon |
| Coordinates | 51.52401, -1.76436 |
Power and grid
| Grid carbon intensity | 218 g CO₂ per kWh (United Kingdom, 2025) Average of all power made in the area. Ember. |
|---|---|
| Grid power mix | gas 31.3%, wind 29.4%, bioenergy 13.9%, nuclear 12.4%, solar 6.6%. Clean power: 64.2% |
Climate and water
| Average temperature | 10 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 34.7 °C (2001 to 2025) |
| Cooling degree days | 33 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 2.94 kWh per m² per day |
| Wind at 50 m | 7.2 m/s average |
| Water stress today | Low - Medium (10-20%) (England) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does AWS Swindon Data Centre use?
We estimate the facility power at about 14 MW. Estimate from building footprint, low confidence.
What chips does AWS Swindon Data Centre use?
No chips are reported. Based on the operator, the likely chips are AWS Trainium and NVIDIA GPUs.
How clean is the power for AWS Swindon Data Centre?
The grid in United Kingdom emits about 218 g CO₂ per kWh (2025). Largest sources: gas 31.3%, wind 29.4%, bioenergy 13.9%.
Who operates AWS Swindon Data Centre?
Amazon Web Services.
Data centers near Swindon
- Vodafone 6.5 km · 8.5 MW
- Nationwide Building Society data center in Swindon 7.3 km · 4 MW
- nLighten Swindon BRS2 9.0 km · 8 MW
- R89 31.5 km · 2.1 MW
- Ark Data Centres - Spring Park - SQ17, P1, P2, P3, P4, P5 33.4 km · 10 MW
- Data center in Neston 33.7 km · 3 MW
- Ark Data Centres 33.9 km · 6.2 MW
- Stream Networks - Newbury 34.0 km
More Amazon Web Services data centers
- Anthropic-Amazon New Carlisle United States
- Amazon Ridgeland United States
- Amazon Madison Mega Site United States
- AWS New Albany United States
- AWS Canton Data Center United States
- AWS Berwick United States
- AWS Ridgeland Data Center United States
- AWS Umatilla Data Center United States
Sources
Correct this page or get the data