Azure OpenAI GPT-3 Cluster is an operational AI data center operated by Microsoft in Quincy, United States. Its power is about 6.6 MW. Epoch AI estimates about 632 H100-equivalent AI chips (NVIDIA V100).

Key facts

StatusOperational
OperatorMicrosoft
Facility power6.6 MW
Reported (Epoch AI or owner data)
AI compute632 H100-equivalents
AI chipsNVIDIA V100
Reported (Epoch AI or owner data)
Chip count10,000
Largest reported cluster at this site (Epoch AI).
GPU capacity if all AIabout 2,800 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Also known asMicrosoft MWH Data Center · Microsoft
Address1515 Port Industrial Way, Quincy, WA 98848
Coordinates47.23792, -119.88497

Power and grid

Nearest high-voltage substationUnnamed substation, 115 kV, 900 m away
Straight-line distance. OpenStreetMap, substations of 100 kV and more.
Nearest 220 kV+ substationUnnamed substation, 230 kV, 1.4 km away
HV substations within 10 km4
UtilityPUD No 2 Of Grant County (political subdivision)
Electric retail service territory (HIFLD, US government).
Balancing authorityGCPD
Nearest gas pipelineNorthwest Pipeline, interstate pipeline, 16.1 km away
US Energy Information Administration pipeline map. Straight-line distance.
Power plants within 50 km3.1 GW in 3 plants
Plants with a stated output in OpenStreetMap. The largest four are listed.
Grid carbon intensity135 g CO₂ per kWh (Washington, 2025)
Average of all power made in the area. Ember.
Grid power mixhydro 62.8%, gas 15.7%, wind 8.3%, nuclear 7.5%, coal 3%. Clean power: 80.9%
Industrial power priceUSD 0.074 per kWh (Washington, August 2026)
Average price paid by industrial users in the state. EIA Electric Power Monthly.

Climate and water

Average temperature9.5 °C
NASA POWER, average of 2001 to 2025.
Highest temperature41.1 °C (2001 to 2025)
Cooling degree days327 per year (base 18.3 °C)
More cooling degree days means more energy for cooling.
Solar energy4.11 kWh per m² per day
Wind at 50 m4.6 m/s average
Water stress todayLow - Medium (10-20%) (Washington)
Share of the local water supply that people already use. WRI Aqueduct 4.0, province level.
Water stress in 2050Low - Medium (10-20%)
Business-as-usual scenario.

GPU clusters at this site

ClusterChipsCountPowerSince
Azure OpenAI GPT-3 ClusterNVIDIA V10010,0006.6 MW2020-04-15

Source: Epoch AI GPU Clusters.

Satellite view

Questions

How much power does Azure OpenAI GPT-3 Cluster use?

Public data puts the facility power at about 6.6 MW. Reported (Epoch AI or owner data).

What chips does Azure OpenAI GPT-3 Cluster use?

Reported chips: NVIDIA V100.

How close is Azure OpenAI GPT-3 Cluster to the power grid?

The nearest high-voltage substation in OpenStreetMap is an unnamed substation (115 kV), about 900 m away. The local utility is PUD No 2 Of Grant County, in the GCPD balancing area.

How clean is the power for Azure OpenAI GPT-3 Cluster?

The grid in Washington emits about 135 g CO₂ per kWh (2025). Largest sources: hydro 62.8%, gas 15.7%, wind 8.3%.

Who operates Azure OpenAI GPT-3 Cluster?

Microsoft.

Data centers near Quincy

More Microsoft data centers

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.