CPH07
CPH07 is an operational data center operated by Microsoft in Taastrup, Denmark. Our footprint estimate of its power is about 21 MW. Likely chips: NVIDIA GPUs (some Microsoft Maia) (guess).
Key facts
| Status | Operational |
|---|---|
| Operator | Microsoft |
| Facility power | 21 MW (range 11 MW to 34 MW) Estimate from building footprint, low confidence. Footprint estimate: about 17,770 m² building outline x 1 floor(s) x 1.2 kW/m². |
| AI chips | NVIDIA GPUs (some Microsoft Maia) Guess from the operator, not confirmed. Microsoft AI capacity is mostly NVIDIA, with a few in-house Maia chips. |
| GPU capacity if all AI | about 9,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Coordinates | 55.64370, 12.25922 |
Power and grid
| Grid carbon intensity | 120 g CO₂ per kWh (Denmark, 2025) Average of all power made in the area. Ember. |
|---|---|
| Grid power mix | wind 56.9%, bioenergy 21.4%, solar 12.8%, oil and other fossil 4.9%, coal 2.5%. Clean power: 91.2% |
| Industrial power price | EUR 0.118 per kWh (Denmark, 2026-S1) Non-household users with 20 to 70 GWh per year, without VAT. Eurostat. |
Climate and water
| Average temperature | 9 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 30 °C (2001 to 2025) |
| Cooling degree days | 44 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 2.91 kWh per m² per day |
| Wind at 50 m | 7.6 m/s average |
| Water stress today | Low (<10%) (Denmark) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | Low (<10%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does CPH07 use?
We estimate the facility power at about 21 MW. Estimate from building footprint, low confidence.
What chips does CPH07 use?
No chips are reported. Based on the operator, the likely chips are NVIDIA GPUs (some Microsoft Maia).
How clean is the power for CPH07?
The grid in Denmark emits about 120 g CO₂ per kWh (2025). Largest sources: wind 56.9%, bioenergy 21.4%, solar 12.8%.
Who operates CPH07?
Microsoft.
Data centers near Taastrup
- GlobalConnect Taastrup 1 (CPH1) 3.3 km · 5.4 MW
- GlobalConnect Taastrup 2 3.7 km
- GlobalConnect Albertslund (CPH3) 7.3 km
- Adeo Datacenter 7.3 km · 4.1 MW
- Norlys Telehouse Copenhagen 7.7 km
- Cibicom Datacenter CPH West 8.2 km
- Penta Infra Copenhagen CPH01 9.6 km
- Aeven data center in Rødovre 11.3 km · 2 MW
More Microsoft data centers
- Microsoft Fairwater Wisconsin United States
- Crusoe Abilene Expansion United States
- Microsoft Fairwater Atlanta United States
- Microsoft Goodyear United States
- Microsoft Boydton Data Center United States
- Microsoft Project Osmium United States
- OpenAI/Microsoft Goodyear Arizona United States
- Microsoft CYS Datacenter United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.