Equinix NY7 - New York, North Bergen
Equinix NY7 - New York, North Bergen is an operational data center operated by Equinix in North Bergen, United States. Our footprint estimate of its power is about 12 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | Equinix |
| Facility power | 12 MW (range 6 MW to 19 MW) Estimate from building footprint, low confidence. Footprint estimate: about 9,930 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 5,100 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Networks | 18 networks, 2 internet exchanges PeeringDB. |
| Also known as | Equinix NY7 Data Center |
| Address | 5851 Westside Ave |
| Coordinates | 40.79686, -74.03113 |
| Website | equinix.com/locations/americas-colocation/united-states-colocation/new-york-data-centers/ny7 |
Power and grid
| Nearest high-voltage substation | North Bergen Substation, 230 kV, 1 km away (PSE&G) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| HV substations within 10 km | 39 |
| Utility | Public Service Elec & Gas Co (investor owned) Electric retail service territory (HIFLD, US government). |
| Balancing authority | PJM |
| Nearest gas pipeline | Transcontinental Gas PL, interstate pipeline, 2.6 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 20 GW in 133 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 265 g CO₂ per kWh (New Jersey, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 45.8%, nuclear 43.2%, solar 9%, oil and other fossil 1.5%, bioenergy 0.9%. Clean power: 52.8% |
| Industrial power price | USD 0.162 per kWh (New Jersey, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 11.1 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 38.7 °C (2001 to 2025) |
| Cooling degree days | 504 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.87 kWh per m² per day |
| Wind at 50 m | 5.3 m/s average |
| Water stress today | Medium - High (20-40%) (New Jersey) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Medium - High (20-40%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Equinix NY7 - New York, North Bergen use?
We estimate the facility power at about 12 MW. Estimate from building footprint, low confidence.
How close is Equinix NY7 - New York, North Bergen to the power grid?
The nearest high-voltage substation in OpenStreetMap is North Bergen Substation (230 kV), about 1 km away. The local utility is Public Service Elec & Gas Co, in the PJM balancing area.
How clean is the power for Equinix NY7 - New York, North Bergen?
The grid in New Jersey emits about 265 g CO₂ per kWh (2025). Largest sources: gas 45.8%, nuclear 43.2%, solar 9%.
Who operates Equinix NY7 - New York, North Bergen?
Equinix.
Data centers near North Bergen
- CoreSite - Secaucus (NY2) 3.2 km · 5.8 MW
- Evocative EWR1 3.3 km · 17 MW
- Centersquare New Jersey (EWR5) 3.4 km · 21 MW
- Sungard AS Carlstadt 777 3.7 km
- InterServer Teb2 3.8 km
- 365 Data Centers Carlstadt (NJ3) 3.8 km
- H5 Secaucus 3.9 km
- Level(3) Weehawken 3.9 km · 76 MW
More Equinix data centers
- Equinix DA1 - Dallas United States
- Equinix SP6 Brazil
- Equinix PH1 - Philadelphia United States
- Equinix PA13X France
- Equinix CH1/CH2/CH4 - Chicago United States
- Equinix CH3 - Elk Grove United States
- Equinix AM3 - Amsterdam, Science Park Netherlands
- Equinix LA1 - Los Angeles United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.