Flexential - Nashville/Brentwood (NAS01/04) is an operational data center operated by Flexential in Brentwood, United States. Our footprint estimate of its power is about 11 MW.

Key facts

StatusOperational
OperatorFlexential
Facility power11 MW (range 4.4 MW to 28 MW)
Estimate from building footprint, low confidence. Footprint estimate: about 92,290 m² site outline x 0.12 kW per m² of land.
GPU capacity if all AIabout 4,700 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Networks1 networks
PeeringDB.
Also known asFlexential Brentwood Data Center · Flexential Nashville - Brentwood
Address7100 Commerce Way, Suite 25,
Coordinates35.97245, -86.80875
Websiteflexential.com

Power and grid

Nearest high-voltage substationUnnamed substation, 161 kV, 3.3 km away (Middle Tennessee Electric)
Straight-line distance. OpenStreetMap, substations of 100 kV and more.
Nearest 220 kV+ substationDavidson Substation, 500 kV, 19 km away
HV substations within 10 km10
UtilityMiddle Tennessee E M C (cooperative)
Electric retail service territory (HIFLD, US government).
Balancing authorityTVA
Nearest gas pipelineGulf Xpress, interstate pipeline, 700 m away
US Energy Information Administration pipeline map. Straight-line distance.
Power plants within 50 km145 MW in 9 plants
Plants with a stated output in OpenStreetMap. The largest four are listed.
Grid carbon intensity363 g CO₂ per kWh (Tennessee, 2025)
Average of all power made in the area. Ember.
Grid power mixnuclear 39.2%, coal 24.1%, gas 23.5%, hydro 10.5%, solar 1.9%. Clean power: 52.2%
Industrial power priceUSD 0.069 per kWh (Tennessee, August 2026)
Average price paid by industrial users in the state. EIA Electric Power Monthly.

Climate and water

Average temperature14.9 °C
NASA POWER, average of 2001 to 2025.
Highest temperature42.7 °C (2001 to 2025)
Cooling degree days923 per year (base 18.3 °C)
More cooling degree days means more energy for cooling.
Solar energy4.23 kWh per m² per day
Wind at 50 m5.2 m/s average
Water stress todayLow - Medium (10-20%) (Tennessee)
Share of the local water supply that people already use. WRI Aqueduct 4.0, province level.
Water stress in 2050Low - Medium (10-20%)
Business-as-usual scenario.

Satellite view

Questions

How much power does Flexential - Nashville/Brentwood (NAS01/04) use?

We estimate the facility power at about 11 MW. Estimate from building footprint, low confidence.

How close is Flexential - Nashville/Brentwood (NAS01/04) to the power grid?

The nearest high-voltage substation in OpenStreetMap is an unnamed substation (161 kV), about 3.3 km away. The local utility is Middle Tennessee E M C, in the TVA balancing area.

How clean is the power for Flexential - Nashville/Brentwood (NAS01/04)?

The grid in Tennessee emits about 363 g CO₂ per kWh (2025). Largest sources: nuclear 39.2%, coal 24.1%, gas 23.5%.

Who operates Flexential - Nashville/Brentwood (NAS01/04)?

Flexential.

Data centers near Brentwood

More Flexential data centers

Sources

Correct this page or get the data

Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.