Microsoft SAT40

Microsoft SAT40 is an operational AI data center operated by Microsoft in San Antonio, United States. Its power is about 106 MW. Epoch AI estimates about 65,000 H100-equivalent AI chips (H100, B300).

Key facts

StatusOperational
OperatorMicrosoft
Facility power106 MW
Reported (Epoch AI or owner data)
IT power75 MW
AI compute65,000 H100-equivalents
AI chipsH100, B300
Reported (Epoch AI or owner data)
GPU capacity if all AIabout 42,000 GPUs
If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count.
Capital costUSD 2.8 billion
Epoch AI estimate, 2025 USD.
Address15000 Lambda Drive, San Antonio, TX 78245
Coordinates29.42460, -98.49514 (city level)

Power and grid

UtilityCity Of San Antonio (municipal)
Electric retail service territory (HIFLD, US government).
Balancing authorityERCO
Nearest gas pipelineEl Paso Texas Pipeline Co, intrastate pipeline, 11.2 km away
US Energy Information Administration pipeline map. Straight-line distance.
Grid carbon intensity379 g CO₂ per kWh (Texas, 2025)
Average of all power made in the area. Ember.
Grid power mixgas 48.3%, wind 21.7%, coal 11.6%, solar 10.7%, nuclear 7%. Clean power: 39.8%
Industrial power priceUSD 0.072 per kWh (Texas, August 2026)
Average price paid by industrial users in the state. EIA Electric Power Monthly.

Climate and water

Average temperature20.6 °C
NASA POWER, average of 2001 to 2025.
Highest temperature44.5 °C (2001 to 2025)
Cooling degree days1,804 per year (base 18.3 °C)
More cooling degree days means more energy for cooling.
Solar energy4.84 kWh per m² per day
Wind at 50 m6.1 m/s average
Water stress todayHigh (40-80%) (Texas)
Share of the local water supply that people already use. WRI Aqueduct 4.0, province level.
Water stress in 2050High (40-80%)
Business-as-usual scenario.

Build timeline

DatePowerH100eWhat the satellite images and filings show
2018-12-2800Land clearing begins for the site, specifically digging up a parking lot and making outlines for the buildings. Evident on [Google Earth](https://earth.google.com/web/@29.4149522,-98.80304495,292.48816289a,1532.49619452d,35y,0h,0t,0r/).
2024-05-2466 MW32,000Building 1 operational. Estimated 3 months out from February, when there was still construction equipment.
2025-12-01106 MW65,000Building 2 operational. No more construction on building, and surrounding roads are also complete.
2026-02-04106 MW65,000Site has already been completed, with no more visible construction on any building.

Source: Epoch AI Frontier Data Centers.

Chip deployments

DateChipUnitsBasis
2024-05-24H10032,407Estimate
2025-12-01B30012,750Estimate

Satellite view

Questions

How much power does Microsoft SAT40 use?

Public data puts the facility power at about 106 MW. Reported (Epoch AI or owner data).

What chips does Microsoft SAT40 use?

Reported chips: H100, B300.

How clean is the power for Microsoft SAT40?

The grid in Texas emits about 379 g CO₂ per kWh (2025). Largest sources: gas 48.3%, wind 21.7%, coal 11.6%.

Who operates Microsoft SAT40?

Microsoft.