NTT Hemel Hempstead 4 Data Center (HH4) is an operational data center operated by NTT Global Data Centers in Hemel Hempstead, United Kingdom. Our footprint estimate of its power is about 24 MW.
Key facts
| Status | Operational |
|---|---|
| Operator | NTT Global Data Centers |
| Facility power | 24 MW (range 12 MW to 38 MW) Estimate from building footprint, low confidence. Footprint estimate: about 19,586 m² building outline x 1 floor(s) x 1.2 kW/m². |
| GPU capacity if all AI | about 10,000 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Also known as | NTT Hemel Hempstead 4 |
| Address | 1 Blossom Way, Hemel Hempstead |
| Coordinates | 51.75791, -0.43108 |
| Website | datacenter.hello.global.ntt/en/location/london/hemel-hempstead-4-data-center |
Power and grid
| Nearest high-voltage substation | Piccotts End Grid, 132 kV, 4 km away (UK Power Networks) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Elstree Substation, 400 kV, 12.4 km away |
| HV substations within 10 km | 4 |
| Power plants within 50 km | 3.1 GW in 107 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 218 g CO₂ per kWh (United Kingdom, 2025) Average of all power made in the area. Ember. |
| Grid power mix | gas 31.3%, wind 29.4%, bioenergy 13.9%, nuclear 12.4%, solar 6.6%. Clean power: 64.2% |
Climate and water
| Average temperature | 10 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 34.3 °C (2001 to 2025) |
| Cooling degree days | 36 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 2.88 kWh per m² per day |
| Wind at 50 m | 7.1 m/s average |
| Water stress today | Low - Medium (10-20%) (England) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Low - Medium (10-20%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does NTT Hemel Hempstead 4 Data Center (HH4) use?
We estimate the facility power at about 24 MW. Estimate from building footprint, low confidence.
How close is NTT Hemel Hempstead 4 Data Center (HH4) to the power grid?
The nearest high-voltage substation in OpenStreetMap is Piccotts End Grid (132 kV), about 4 km away.
How clean is the power for NTT Hemel Hempstead 4 Data Center (HH4)?
The grid in United Kingdom emits about 218 g CO₂ per kWh (2025). Largest sources: gas 31.3%, wind 29.4%, bioenergy 13.9%.
Who operates NTT Hemel Hempstead 4 Data Center (HH4)?
NTT Global Data Centers.
Data centers near Hemel Hempstead
- NTT Hemel Hempstead 3 Data Center (HH3) 586 m · 21 MW
- NTT Hemel Hempstead 1 Data Center (HH1) 738 m
- NTT Hemel Hempstead 2 Data Center (HH2) 1.1 km · 11 MW
- BT Computer Centre 7.7 km · 4 MW
- The Chess Building 12.8 km · 17 MW
- Elstree Customer Hosting Centre 15.6 km
- ServerChoice SC-2 16.2 km
- Data center in Dunstable 16.3 km · 8.6 MW
More NTT Global Data Centers data centers
- NTT VA10 United States
- NTT Frankfurt 2 Data Center (FRA2) Germany
- NTT PH1 Datacenter United States
- NTT Japan
- NTTData Data Center United States
- NTT Berlin 1 Data Center (BER1) Germany
- NTT London 1 United Kingdom
- NTT RagingWire DC - Hillsboro United States
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.