NTT Munich 1 Data Center (MUC1)
NTT Munich 1 Data Center (MUC1) is an operational data center operated by NTT Global Data Centers in Munich, Germany. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | NTT Global Data Centers |
| Networks | 3 networks PeeringDB. |
| Address | Ammerthalstrasse 10 |
| Coordinates | 48.15011, 11.74795 |
| Website | datacenter.hello.global.ntt/en/location/munich/munich-1-data-center |
Power and grid
| Nearest high-voltage substation | Landsham, 110 kV, 3.7 km away (Bayernwerk Netz) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Hauptumspannwerk Föhring, 380 kV, 8.7 km away |
| HV substations within 10 km | 14 |
| Power plants within 50 km | 3.0 GW in 63 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 334 g CO₂ per kWh (Germany, 2025) Average of all power made in the area. Ember. |
| Grid power mix | wind 26.6%, coal 21%, solar 18%, gas 16.8%, bioenergy 10.1%. Clean power: 58.5% |
| Industrial power price | EUR 0.146 per kWh (Germany, 2026-S1) Non-household users with 20 to 70 GWh per year, without VAT. Eurostat. |
Climate and water
| Average temperature | 8.6 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 36.2 °C (2001 to 2025) |
| Cooling degree days | 108 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.25 kWh per m² per day |
| Wind at 50 m | 4.5 m/s average |
| Water stress today | Medium - High (20-40%) (Germany) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | Medium - High (20-40%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is NTT Munich 1 Data Center (MUC1) to the power grid?
The nearest high-voltage substation in OpenStreetMap is Landsham (110 kV), about 3.7 km away.
How clean is the power for NTT Munich 1 Data Center (MUC1)?
The grid in Germany emits about 334 g CO₂ per kWh (2025). Largest sources: wind 26.6%, coal 21%, solar 18%.
Who operates NTT Munich 1 Data Center (MUC1)?
NTT Global Data Centers.
Data centers near Munich
- noris Munich MUC5 1.5 km · 5.5 MW
- noris network datacenter.de MUC5 1.8 km
- Portus MUC1 1.8 km
- Equinix MU4 - Munich, Dornach 4.9 km · 1.9 MW
- WIIT Datacenter MUC8 5.1 km
- NorthC Munich 2 6.5 km · 7.3 MW
- Data center in Unterföhring 9.3 km · 2.3 MW
- Telekom Data-Center 11.1 km · 29 MW
More NTT Global Data Centers data centers
- NTT VA10 United States
- NTT Frankfurt 2 Data Center (FRA2) Germany
- NTT PH1 Datacenter United States
- NTT Japan
- NTTData Data Center United States
- NTT Hemel Hempstead 4 Data Center (HH4) United Kingdom
- NTT Berlin 1 Data Center (BER1) Germany
- NTT London 1 United Kingdom
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.