Serverfarm CH2 Oak Brook / Chicago
Serverfarm CH2 Oak Brook / Chicago is an operational data center operated by Serverfarm in Oak Brook, United States. No power figure is public for this site yet.
Key facts
| Status | Operational |
|---|---|
| Operator | Serverfarm |
| Networks | 6 networks, 3 internet exchanges PeeringDB. |
| Also known as | NYI CH1 (800 Jorie Blvd) |
| Address | 800 Jorie Blvd |
| Coordinates | 41.84534, -87.94152 |
| Website | serverfarmllc.com/data-centers/oakbrook-data-center |
Power and grid
| Nearest high-voltage substation | Unnamed substation, 138 kV, 900 m away (Commonwealth Edison) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Unnamed substation, 345 kV, 8.7 km away |
| HV substations within 10 km | 16 |
| Utility | Commonwealth Edison Co (investor owned) Electric retail service territory (HIFLD, US government). |
| Balancing authority | PJM |
| Nearest gas pipeline | Northern Illinois Gas Co, intrastate pipeline, 1.2 km away US Energy Information Administration pipeline map. Straight-line distance. |
| Power plants within 50 km | 8.9 GW in 41 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 247 g CO₂ per kWh (Illinois, 2025) Average of all power made in the area. Ember. |
| Grid power mix | nuclear 49.9%, gas 16.6%, coal 15.8%, wind 12.8%, solar 4.5%. Clean power: 67.3% |
| Industrial power price | USD 0.113 per kWh (Illinois, August 2026) Average price paid by industrial users in the state. EIA Electric Power Monthly. |
Climate and water
| Average temperature | 9.5 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 40.5 °C (2001 to 2025) |
| Cooling degree days | 465 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 3.67 kWh per m² per day |
| Wind at 50 m | 6.8 m/s average |
| Water stress today | Medium - High (20-40%) (Illinois) Share of the local water supply that people already use. WRI Aqueduct 4.0, province level. |
| Water stress in 2050 | Medium - High (20-40%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How close is Serverfarm CH2 Oak Brook / Chicago to the power grid?
The nearest high-voltage substation in OpenStreetMap is an unnamed substation (138 kV), about 900 m away. The local utility is Commonwealth Edison Co, in the PJM balancing area.
How clean is the power for Serverfarm CH2 Oak Brook / Chicago?
The grid in Illinois emits about 247 g CO₂ per kWh (2025). Largest sources: nuclear 49.9%, gas 16.6%, coal 15.8%.
Who operates Serverfarm CH2 Oak Brook / Chicago?
Serverfarm.
Data centers near Oak Brook
- US Signal - Oak Brook 188 m
- CDC4 - 1808 Swift Dr 2.0 km
- Equinix CH7 - Westmont 4.5 km · 4.3 MW
- CyrusOne Chicago (Lombard) 7.3 km
- Aligned Chicago (ORD-01) 7.8 km
- Aligned Data Center - Chicago ORD-01 7.9 km · 18 MW
- Ascent - CH2 8.7 km
- Microsoft - Azure Datacenter 8.8 km · 28 MW
More Serverfarm data centers
- Serverfarm CH1 Chicago United States
- Serverfarm LAX1 Los Angeles United States
- Serverfarm LON1 – London Data Center United Kingdom
- ServerFarm SC1 United States
- Serverfarm AMS1 Amsterdam Netherlands
- Serverfarm ATL1 Atlanta United States
- Serverfarm TiTAN Moses Lake United States
- Serverfarm TOR1 Toronto Canada
Sources
Correct this page or get the data
Do you know this site? Send a correction, a power figure or a chip count. Do you need the full dataset, power demand by region, or a list of sites that need power? Leave your email.