Google Data Center
Google Data Center is an operational data center operated by Google in Quilicura, Chile. Our footprint estimate of its power is about 18 MW. Likely chips: Google TPU (plus NVIDIA GPUs for cloud customers) (guess).
Key facts
| Status | Operational |
|---|---|
| Operator | |
| Facility power | 18 MW (range 7.4 MW to 46 MW) Estimate from building footprint, low confidence. Footprint estimate: about 153,211 m² site outline x 0.12 kW per m² of land. |
| AI chips | Google TPU (plus NVIDIA GPUs for cloud customers) Guess from the operator, not confirmed. Google runs most of its AI work on its own TPU chips. |
| GPU capacity if all AI | about 7,700 GPUs If all IT power ran GB200-class GPUs at 1.8 kW each, all-in (PUE 1.3). An upper bound, not a count. |
| Coordinates | -33.35838, -70.69485 |
Power and grid
| Nearest high-voltage substation | Unnamed substation, 110 kV, 1.5 km away (Enel Distribución Chile) Straight-line distance. OpenStreetMap, substations of 100 kV and more. |
|---|---|
| Nearest 220 kV+ substation | Unnamed substation, 220 kV, 6.2 km away |
| HV substations within 10 km | 12 |
| Power plants within 50 km | 1.2 GW in 83 plants
Plants with a stated output in OpenStreetMap. The largest four are listed. |
| Grid carbon intensity | 291 g CO₂ per kWh (Chile, 2025) Average of all power made in the area. Ember. |
| Grid power mix | solar 25.1%, hydro 22.2%, coal 17.8%, gas 15.3%, wind 13.1%. Clean power: 66.4% |
Climate and water
| Average temperature | 15.3 °C NASA POWER, average of 2001 to 2025. |
|---|---|
| Highest temperature | 37.9 °C (2001 to 2025) |
| Cooling degree days | 445 per year (base 18.3 °C) More cooling degree days means more energy for cooling. |
| Solar energy | 5.42 kWh per m² per day |
| Wind at 50 m | 3.2 m/s average |
| Water stress today | Extremely High (>80%) (Chile) Share of the local water supply that people already use. WRI Aqueduct 4.0, country level. |
| Water stress in 2050 | Extremely High (>80%) Business-as-usual scenario. |
Satellite view
Google satellite · Copernicus Sentinel-2 history · OpenStreetMap
Questions
How much power does Google Data Center use?
We estimate the facility power at about 18 MW. Estimate from building footprint, low confidence.
What chips does Google Data Center use?
No chips are reported. Based on the operator, the likely chips are Google TPU (plus NVIDIA GPUs for cloud customers).
How close is Google Data Center to the power grid?
The nearest high-voltage substation in OpenStreetMap is an unnamed substation (110 kV), about 1.5 km away.
How clean is the power for Google Data Center?
The grid in Chile emits about 291 g CO₂ per kWh (2025). Largest sources: solar 25.1%, hydro 22.2%, coal 17.8%.
Who operates Google Data Center?
Google.
Data centers near Quilicura
- SONDA - Quilicura 443 m · 2.1 MW
- Cirion Santiago de Chile - SAN1 1.7 km · 1.2 MW
- Microsoft Data Center 2.3 km · 11 MW
- Ascenty SCL01 - Santiago 2.4 km
- Ascenty SCL02 - Santiago 2.5 km
- Campus Santiago Ascenty Data Center 2.7 km · 11 MW
- GTD Chile - Panamericana 3.3 km
- Data Center GTD 4.5 km · 3.1 MW
More Google data centers
- Goodnight United States
- Google Fort Wayne United States
- Google Omaha United States
- Google Columbus United States
- Google Pryor (North) United States
- Google New Albany United States
- Google Storey County United States
- Google Lincoln United States
Sources
Correct this page or get the data